Why Can't the MTA Run on Time [Poll]

The MTA's "East Side Access" plan may be delayed until 2019.

The now says its tunnel project to provide LIRR riders direct access to Grand Central Terminal might be delayed until 2019.

The MTA says problems have emerged beneath Jamaica Station, including contaminated soil and unexpected underground water sources. The project was originally planned for completion in 2015. The authority has brought in tunneling experts from Europe to help solve the problems.

The East Side Access project would cut some 40 minutes from a typical journey made by LIRR riders whose ultimate destination is the East Side of Manhattan. Now, all LIRR trains end at Penn Station, on the West Side. If you've ever tried to get to Grand Central from Hicksville - either by cab from Penn Station or by subway from Jamaica, you know what we mean.

Why does it seem the can't get things done on time?

Why do problems always seem to crop up with their ?

Take our poll and sound off in the comments:

 

Gary Talkofsky May 09, 2012 at 03:54 PM
I thought the problem is in the Sunnyside yards not Jamaica.
Joe Dowd (Editor) May 10, 2012 at 04:01 AM
Gary: I checked. The problem is beneath Jamaica and westward. They are citing issues with underground streams and springs in that area. They are also talking about contaminated soil that would have to be removed.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something